Your house lifting process & timeline.

Understand all eight stages, the construction schedule and the time to plan away from home.

Preconstruction timeline

1216 weeks

Design & engineering through permitting · Steps 1–2

Construction timeline

1935 weeks

Structural preparation through lower level completion · Steps 3–8

Time out of home

1321 weeks

Structural preparation through structural set down · Steps 3–7

Planning totals add the step ranges below. Steps may overlap, and schedules vary. Return home after set down depends on utilities, safe access and required occupancy approvals.

STEP 01 / 08GROUND / FOUNDATION SECTION
Structural steelTemporary cribbingPermanent foundation

FROM THE GROUND UP

Design & Engineering

Typical duration6 to 8 weeks

Assumes the homeowner makes decisions and responds promptly.

Evaluate the existing structure, survey, soils and desired elevation. Develop the engineered lifting, support and permanent foundation plans.

STAGE 01

Design & Engineering

Typical duration6 to 8 weeks

Assumes the homeowner makes decisions and responds promptly.

Evaluate the existing structure, survey, soils and desired elevation. Develop the engineered lifting, support and permanent foundation plans.

STAGE 02

Permitting

Typical duration6 to 8 weeks

Submit the required plans and supporting documents. Address building, zoning and floodplain reviews and obtain required approvals before the applicable work begins.

STAGE 03

Structural Preparation

Typical duration3 to 4 weeks

Prepare the structure and site for the engineered sequence, including required separation work, access and utility disconnections.

STAGE 04

Excavation & Support Installation

Typical duration2 to 6 weeks

Varies with crawlspace or slab-on-grade construction and site interferences such as tree roots.

Excavate as required and install the engineered steel, lifting equipment and temporary supports beneath the structure.

STAGE 05

Elevation

Typical duration1 to 2 weeks

Raise the structure in a controlled sequence using the engineered lifting system. Maintain stable temporary support at the planned elevation.

STAGE 06

Foundation Installation, Pilings, Footings, Piers

Typical duration6 to 8 weeks

Install the permanent foundation specified by the engineer. Pilings, footings and piers are used where required by the design, with permanent supports positioned clear of temporary cribbing.

STAGE 07

Structural Set Down

Typical duration1 week

Homeowners may move back in after set down once utilities, safe access and any required occupancy approvals are in place.

Transfer the structure onto its permanent supports, complete the designed connections and remove temporary lifting equipment and cribbing in the approved sequence.

STAGE 08

Lower Level Completion

Typical duration6 to 14 weeks

Varies with the extent of finishes the homeowner asks JAS to complete.

Complete the contracted lower slab, permitted enclosure, decks, stairs, utilities and finishes. Obtain required inspections and occupancy approvals.

JAS manages and constructs the project. The selected specialized lifting team performs the physical lift and set. The sequence is illustrative: engineering and site conditions determine actual methods, support and order.

Follow the Work.

LET’S START WITH YOUR HOME

What are you
ready to change?

Tell us where you are, what you have, and what you want your home to become.

Schedule a Consultation →Or call (727) 607-8813
Call JASRequest Estimate →