Watching a whole house rise off the ground is something people do not forget. Here is what is actually happening, step by step, from the first beam to the day you move back in.
1. Preparing the house
Before anything goes up, the house is disconnected from the ground. Utilities are shut off and disconnected where they enter the house. Plants, pavers or decks in the way may be removed. Inside, we will talk with you about what can stay and what should be packed, especially fragile and heavy items.
2. Getting steel under the house
Steel beams go under the house to carry it during the lift. For a wood frame house on a crawl space, that can mean sliding beams under the floor framing. For a slab-on-grade home, it means openings are cut so beams can go under the slab, and the slab and walls are lifted together as one unit. The engineering decides where the beams go and how the load is spread so the house moves as one piece.
3. Jacks and cribbing
Hydraulic jacks lift the house a little at a time, and stacks of timber called cribbing are built up underneath as it rises. The jacks are linked so the house goes up evenly. It is slow on purpose. Keeping the house level and moving it gradually is what protects it.
4. Temporary shoring
Once the house reaches its new height, it rests on temporary supports while the permanent foundation is built underneath. This is the stage when nobody can live in the home. The house is safe on its supports, but it is a construction site, and utilities are disconnected.
5. The new foundation
The permanent foundation is built under the raised house. Depending on the soil and the design, that may be shallow footings or deep foundations such as piles, with piers or columns rising to the house. The engineer designs the connections that tie the house to the new foundation, including protection against wind uplift.
6. Setting the house down
The house is lowered onto its permanent supports and connected. The temporary steel and cribbing come out.
7. Utilities, stairs and the area below
Plumbing, sewer, electric, gas and AC are reconnected. Some lines can be reused, and some have to be replaced or rerouted. The electric meter and AC equipment often have to be raised, and the power company may decide whether the service moves or goes underground. New stairs, landings and decks give safe access, and the area under the house is finished for parking or storage as the rules allow.
8. Inspections and moving back in
Final inspections, including an Elevation Certificate, confirm the house meets the approved plans. Then you can move back in.
Will it crack?
Moving a house can cause some cracking in drywall, stucco, tile or masonry, and doors and windows may need adjusting afterward. Careful engineering and a slow, level lift keep that to a minimum, and a good agreement says how finish repairs are handled. Heavy, brittle parts like brick veneer and chimneys get special attention in the plan.
What if a storm comes?
Weather is part of the plan from the start. The temporary supports are designed for the conditions the house will face, and the schedule tries to keep the house in the air for as short a time as possible.
See it for yourself
Jeff explains slab support, jacks and cribbing, temporary shoring and the new foundation in short clips in our video library. To talk about your home, call JAS at (727) 607-8813.
Watch Jeff explain it
From the JAS podcast. See all 18 videos.
Share this story
JAS Builders FAQ | https://jasbuilder.com/faq
JAS house lifting video library | https://jasbuilder.com/education/podcast
Comments
No comments yet. Ask a question or share your story.
More from the blog
Planning to lift your home before the 2027 hurricane season? Start the paperwork now
Elevate FloridaElevate Florida: more than $173 million approved for over 465 homes. What approved homeowners do next
Elevate FloridaElevate Florida's cost share, in plain words: the 75/25 split and how flood insurance ICC can help
Get the JAS newsletter
One email a month: Elevate Florida updates, flood insurance changes, grants and what we are building. Unsubscribe any time.
Schedule a Consultation